House Renovation - Dublin 4, Sept 2008
A house renovation in Dublin 4 required internal piling to facilitate a new load bearing wall. Access was extremely limited with access via a standard doorway. The floor was exposed by the main contractor enabling us to complete the internal piling in one day.
- 4No 219mm piles
- Average 5m deep
- Up to 250kN SWL
- Zero Spoil
- No wasted pile cut off generated
- Restricted access
An single story extension was also required at the same property. Using the same mini piling rig as for the internal works the external piling wascompleted in a single day.
- 4No 219mm piles
- Average 5m deep
- Up to 250kN SWL
- Zero Spoil
- No wasted pile cut off generated